BSkyB Ltd

Description
Site 1 was the refit and upgrade of an existing 5000m² office to accommodate 1000 staff. Site 2 was the refit and upgrade of an existing 3500m² office to accommodate 600 staff.

AMS Ltd undertook a full redesign of the Building’s M&E infrastructure required to suit new space plans. This included small power, lighting, security, fire alarms, domestic water, drainage, Air conditioning & refrigeration. Crucial design areas were the specification and installation of a new resilient power generator and UPS back up systems, fit out of new computer rooms, new kitchen and cafeterias and enhancing the air-conditioning systems to accommodate the additional numbers.

Location
Scotland and North of England

Services Provided
Mechanical and Electrical Design

Programme
18 to 20 Weeks Each

Specification
CIBSE and Tier III (Uptime Institute)

Project Value
£750,000 – £1million Each (M&E Only)